+ Monot 38
+ OAKRIDGE Faqra
 |
Oakridge is a breath of freshness within the mountains of Faqra, reflecting the image of a friendly low-density residential and leisure community comfortably settled into a natural hillside overlooking a vista of cascading slopes extending into the distant coastline Click for more... |
+ Silver Rocks Residences
+ The Capital Gardens
 |
The Capital Gardens, in the trendy Mina El Hosn area, is a luxurious residential project in on of the finest areas of Beirut Central District.
Click for more... |
+ The Pavilions
 |
The Pavilions, a residential building serviced by a true life of
natural district and relaxation but also a privileged life of a new district to
the town, planning entirely dedicated to its residents.
Click for more... |
+ Saifi Pearl
 |
Saifi Pearl offers the functionality of a modern architecture, the
approval of materials and quality in services are guaranteed by one of the
leaders name in the construction Mouawad Investment Group.
Click for more... |
+ The Palladium
 |
The lot is much like an island. It is surrounded by four roads. An open air landscaped patio in the middle acts as a relaxing and gathering area for all tenants of the project.
Click for more... |
+ Country Lodge
 |
Country Lodge makes its home in Bsalim, amidst lush nature. easily
accessible from Jal El Dib Highway, and only a short drive down to Beirut
Central District (10 min) and up the mountain towards broumana (5min) , this
pratical location lets you break free from and to the chaotic city. Enter a
world where your well-being comes first.
Click for more... |
|
|
 |
 |
| |
- Residences are expected to be delivered in August 2010.
- Offices and Shops are ready for delivery.
|
|
 |
+ Saifi suites
| + |
Concrete works have reached the roof floor. |
| + |
All concrete works are expected to be completed within 3 weeks. |
| + |
Masonry and Electromechanical works are in progress. |
| + |
A mockup room will be done very soon. |
| + |
Project is expected to be operational in June 2011. |
+ Oakridge Faqra
| |
 |
| + |
Excavation works are almost completed. |
| + |
Concrete works has started now in the residences zone. Raft foundation of residence D will be poured on Tuesday June 1st, 2010. |
| + |
The Lodge, Annexes and Condos, mobilization to start on site next week. Concrete works in this area are expected to begin within a month. |
| + |
A concrete plant is now being installed on site and is expected to start concrete production within 2 weeks. |
Click for more... |
| |
+ Silver Rocks Faqra
| |
 |
| + |
Excavation of roads is almost completed. |
| + |
All retaining walls are completed. |
| |
| |
+ The Palladium
The project is expected to be delivered and operational between June and July 2010.
| |
 |
| + |
Cladding is 75% completed. |
| + |
External tiling for entrances is expected to be done by mid of July. |
| + |
Landscaping to be completed by end of August. Meanwhile all irrigation and electrical works will be completed. |
| + |
All works in basements are already completed and parking is ready to receive cars. Parking management system to be operational in 3 months. |
| + |
All electromechanical equipments (Generators, Fans, Pumps, Smoke detectors, Cctv, Lifts, Pabx, Lighting, Control room, Chillers, Boilers, etc…) are almost completed and will be operational by end of June. |
Block A
| + |
Block A will be completed by end of June and scaffolding will be dismantled. |
| + |
Aluminum and glazing are expected to be completed by end of July, except the Ground Floor. |
Block B & C
| + |
Aluminum and glazing are expected to be completed by end of July, except the Ground Floor. |
| + |
Concrete works are completed. |
| + |
Electromechanical works are in progress in basement floors, common areas and residences. |
| + |
Electromechanical equipments are delivered to site and are being installed. |
| + |
Generators are expected to be delivered to site by the end of November 2009. |
| + |
Plastering works inside residences have reached the 5th floor. |
| + |
External plastering works prior to cladding is almost completed. |
| + |
Installation of aluminum subframes for the residences is almost completed. |
| + |
Completion date is expected by the end of November 2009 in the offices blocks A & B. |
| + |
Installation of the metallic bridges between blocks A & B has started. |
| Click for more... |
|
|
|