+ Silver Rocks
+ Saifi Suites
 |
The intimacy of home, the luxury of a hotel
Being only five minutes away from Beirut Central District, Saifi Suites' location makes of it the only luxurious hotel suites in the area for tourists and business travelers alike. |
+ Jadev residences
+ Monot 38
+ OAKRIDGE Faqra
 |
Oakridge is a breath of freshness within the mountains of Faqra, reflecting the image of a friendly low-density residential and leisure community comfortably settled into a natural hillside overlooking a vista of cascading slopes extending into the distant coastline
Click for more... |
+ Country Lodge
 |
Country Lodge makes its home in Bsalim, amidst lush nature. easily
accessible from Jal El Dib Highway, and only a short drive down to Beirut
Central District (10 min) and up the mountain towards broumana (5min) , this
pratical location lets you break free from and to the chaotic city. Enter a
world where your well-being comes first.
Click for more... |
|
|
 |
 |
| |
- Oakridge Mountain Resort are expected to be delivered in December 2012.
|
|
+ Oakridge
| |
 |
| + |
Excavation works for the 3 villas are expected to be completed by October 2011; |
| + |
Excavation works are now concentrated on gardens and infrastructure; |
| + |
All masonry works in residences A, B, C, D & E are expected to be completed by August 2011; |
| + |
Electro-mechanical works have started in all residences on all levels; |
| + |
Landscape walls at boundary have started; |
| + |
Roof tiles are expected to start by the 1st week of August 2011; |
| + |
Cladding are expected to start by October 2011; |
| + |
Concrete works of the outdoor pool are in progress, expected completion date is by the end of September 2011.
|
| The Residences |
|
| + |
Concrete works in residences A, B, C, D & E are completed. |
| + |
External plaster works have started in residence C. |
| + |
Bathroom tiling has started in residence D. |
| |
Block F: |
| + |
Concrete works have started; |
| + |
The 1st slab, which is the cover of the 2nd basement, will be poured by August 2011.
|
| The Townhouses |
|
| + |
Concrete works on Townhouses 1 & 2 are completed; Expected completion date of the concrete works for: Townhouses 3 & 4 is by August 2011; and Townhouses 5 & 6 is by September 2011.
|
| The Condos |
|
| + |
Concrete works on the 1st and 2nd levels are completed; Expected completion date of the concrete works for: 3rd level is by August 2011; and Roof level is by September 2011.
|
| The Lodge |
|
| + |
Concrete works are expected to reach the attic floor level by September 2011.
|
| The Annex |
|
| + |
Concrete works are expected to reach the attic floor level by August 2011.
|
Click for more... |
| |
+ The Palladium
|
 |
| + |
The project is completely operational on all levels. |
| |
+ Silver Rocks
| |
 |
| The below works have been completed: |
|
| + |
All roads excavation; |
| + |
All retaining walls; |
| + |
Sewage manholes and pipes; |
| + |
Part of domestic and portable water manholes and pipes.
|
| The remaining and undergoing works to be achieved are: |
|
| + |
Completion and modification of the remaining domestic and potable network; |
| + |
Execute low voltage and low current network; |
| + |
Execute rain water network. |
| |
| |
+ Monot 38
| + |
Shoring and excavation works are still in progress. |
| |
+ Saifi Suites
| + |
Concrete works and exterior plastering are completed; |
| + |
Tiling, false ceiling and painting works are in progress; |
| + |
Cladding and Wood works are in progress; |
| + |
Electro-mechanical works in basement floors are in progress; |
| + |
Two mock-up rooms are available. |
| + |
The project is expected to be operational by end of November 2011. |
| |
|
|
|